Precast Concrete Panel Repair
The Problem
A large office warehouse complex whose buildings were constructed of tiltup concrete
wall panels and wood joist roof system supported internally by pipe columns had
contracted to have the exterior surface painted. The painting contractor had realized
that there were an unusually large number of areas on the concrete walls that had
delaminations. Although the painting contractor had no experience in structural
repair, the owner elected to contract with an engineering firm that specialized
in structural repair of buildings and put the painting contractor on a Time and
Material contract to perform the repair with the engineering firm overseeing the
work. After spending $3,000,000.00 and only completing 50% of the work, the owner
stopped the work and canceled the existing contracts. The problem was compounded
because the tenants were upset by the fact that the contractor was an impediment
to their operations and was taking too long to finish the project.
The Solution
The original wall panel design incorporated a bent within the panel. The bent consisted
of a beam along the top of the panel with columns on each side of the panel. The
steel within the bent was corroding excessively due to calcium chloride that had
been used in the original concrete mix. The beam connections from panel to panel
provided a continuous frame around the perimeter of the building along the roof
line. To satisfy the seismic requirements of the building code the wall system and
the roof diaphragm had to be tied together. The engineer designed a wood truss system
to augment the beam that was in the wall panel and then tied it to the all and the
roof diagram. Restruction Corporation developed a construction engineered solution
to install the wood truss system with a minimum impact on the tenants operations.
The extensive network of delaminations throughout the wall panels that had been
excavated needed to be repaired. Several repairs that had been performed with shotcrete
were severely cracked. Although the owner and the city were opposed to shotcrete
because of so many bad experiences, we were able to convince them to allow us to
demonstrate our capability in a few of the cavities. Shotcrete was going to save
a great deal of time and money if we could perform to the satisfaction of all the
parties. After several test panels and demonstration areas the engineer, the owner,
and the city gave their approval.
The texture of the exposed concrete surface varied within the panels and from panel
to panel. To standardize the surface texture Restruction Corporation developed a
cementitious/latex skin coat. The engineer then stipulated that the surface was
to be sealed with a silane sealer and then coated with a coat of paint. Several
paints were tested before one was selected. The entire building was then painted
and completed to the satisfaction of the owner and the job of the tenants.
Project Images