Hydro-Demolition
The Problem
High chloride contents at the level of the reinforcing steel was causing corrosion.
The conventional reinforcing had approximately 1 1/2" of cover. The slab was constructed
as an 8-inch thick plate with beam and column supports. The area of the slab was
11,000 square feet and is used as a loading dock to supply a high rise office tower.
The Solution
Concrete removal of 3 1/2-inches using hydro-demolition was employed. Hydro-demolition
removal was completed over a single weekend using 24-hour shifts. (Removal rate
approximately 60ft2/hour). Hydro-demolition was chosen as the main surface preparation
method due to production speed and the improved bonding characteristics it can provide.
Project Images
Hydro-demolition robot set-up
A large area for pumps and hoses generally required
An industrial vacuum truck will remove waste water
Minor removal of remaining concrete is required