Concrete repair case studies structural repair structural repair structural repair structural repair structural repair

Hydro-Demolition

The Problem

High chloride contents at the level of the reinforcing steel was causing corrosion. The conventional reinforcing had approximately 1 1/2" of cover. The slab was constructed as an 8-inch thick plate with beam and column supports. The area of the slab was 11,000 square feet and is used as a loading dock to supply a high rise office tower.

The Solution

Concrete removal of 3 1/2-inches using hydro-demolition was employed. Hydro-demolition removal was completed over a single weekend using 24-hour shifts. (Removal rate approximately 60ft2/hour). Hydro-demolition was chosen as the main surface preparation method due to production speed and the improved bonding characteristics it can provide.


Project Images

Hydro-demolition robot set-up
Hydro-demolition robot set-up
A large area for pumps and hoses generally required
A large area for pumps and hoses generally required
An industrial vacuum truck will remove waste water
An industrial vacuum truck will remove waste water
Minor removal of remaining concrete is required
Minor removal of remaining concrete is required