Hoover Dam Bypass Bridge
- Concrete arch bridge
- 1,900 feet long
- Concrete arch – 1,000 feet
- Pier caps are 7’ wide x 10’ deep x72’ long
Fire Damage
- Fire Damage to east pier
- Welding on top of pier cap
- Sparks caused form work to smolder
- Formwork smolder over weekend
- Fire damage to underside of pier cap
Repair MethodGoal:
Achieve a durable repair
- Remove damaged concrete using chipping hammers & hydrodemolition
- Perform final preparation using hydrodemolition
- Place new concrete using shotcrete method
Hydrodemolition Issues
- 100% Tie off – Fall Protection
- Accessibility – Handlance
- Close working distance
- PPE for handlance use.
Project PPE
- Fall Protection – 100% tie off using double lanyard
- Full Body armor
- Waterproof steel toe boots with metatarsal protection
- Rain suit
- Waterproof gloves
- Hearing protection
- Hardhat
- Safety Glasses
- Face shield while blasting
Shotcrete Repair
Shotcrete was the recommend repair:
- Accessibility
- Quantity of material
- Durability
FHWA Required Testing
- Mix design submittal
- Material Certifications
- Compressive strength
- Test panels for core grading
- Shrinkage testing
- Bond testing performed on field mockup
Shotcrete Specifications
- Compressive Strength 6000 psi
- Low to moderate shrinkage
- Bond strength of
Material
Selected a pre-blended material:
- Type 1 Portland Cement
- Silica-fume
- Aggregate –ACI 506.2 –Gradation #2
- Design strength of 7,250 psi
Shrinkage
Shrinkage requirement: Low to Moderate
- Cast 3 -3”x3”x11-1/4” prisms
- Drying shrinkage measurements at 7, 14, 21 & 28 days
- Avg. results –0.047%, 0.064%, 0.075% and 0.076%
- ICRI TG 3733
- –Low shrinkage = 0.025 –0.050%–
- Moderate shrinkage = 0.050% -0.10%
- Meets requirement
Test Panel Preparation
Three test panels were prepared to perform various test:
- One unreinforced panel –wood form
- One reinforced panel containing #11 bars @ 10” OC and #4 stirrup bars @ 6” OC –wood form
- One reinforced concrete test panel made at the project site and shipped to the repair contractor’s site
Test Panel – 1
- Unreinforced panel
- Core grading –ACI 506.2 –Grade 2 or better –Excellent Results
- Compressive strength –average 8,180 psi
Test Panel – 2
- Reinforced panel
- Core grading –ACI 506.2 –Grade 2 or better –Excellent Results
- Core visually graded by FHWA officials.
Test Panel – 3
Reinforced concrete panel, water blasted with 20,000 psi to simulate hydrodemolition profile.
- Bond test –ICRI TG 3739
- Average direct tensile strength –259 psi @ 14 days
- Shotcrete Approved for Repairs
Shotcrete Repairs
- Approx. 60 cubic feet installed
- Ridley C-9 dry mix gun•375 cfm
- Shotcrete work accepted
- Construction continues
- Schedule completion of the arch bridge mid-2010
- Open to traffic by the end of 2010
Arch under construction